Ashworth 5-Unit Rowhouse
Project Status Report
August 13, 2021
Overall Status: Green
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Eventful week! This week’s report is a consolidation of this past week and the week prior (ending 8/6).
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Weeks Ending 8/6 & 8/13 |
● Plumbing & Electrical Groundwork wrapped up, was inspected and passed for slab pour ● Water and Sewer Lines were put in, inspected and signed off for backfill ● Slab insulation and vapor barrier was installed in preparation for slab pour. ● Thickened footings were prepared for final slab pour ● City of Seattle signed off on all preparation for slab pour ● Slabs poured and saw cut for expansion joints. ● North side of property (between retaining wall and shoring blocks filled in and compacted with structural fill ● First lumber drop took place (NOTE: Our entire package dropped from $160k to $116k – great news!) ● Framing crew mobilized and have begun with mud sills and laying out walls ● Structural HW was placed onsite for the first floor ● Recycling container onsite and will remain throughout the job (Built Green Approved Vendor) ● Started conversation with Painting Contractor to handle interior and exterior |
Upcoming Activity Preview Week Ending 8/20 |
● Framing to continue (for the next 6 weeks) ● Second lumber drop scheduled for Tuesday ● Dirtwork to continue with backfill – Machine will be delivered onsite – Monday ● Cabinetry refinement and pricing to continue ● HVAC bid refinement – still outstanding and needs to be refined ● Electrical sub will refine estimate based on engineering plans – still outstanding ● Kick off Unit Lot Subdivision ● Start process for Water and Gas Metering |
Contracts: |
● Framing contract executed ● Roofing contract executed ● Siding contract executed ● Masonry contract executed ● Windows Ordered – 2-part delivery – September & October ● Plumbing contract executed |
Change Order Log (Full Summary on File): |
● Plumbing labor change order for trenching and pipe relocation – $2500
|
Open Questions: |
● Unit Lot Subdivision – B9 Architect needs to provide CAD’s and updated PDF’s |