Arbor Heights 9-Unit Townhome

Project Status Report

February 28, 2022

Overall Status: Green

Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin

Project Update:
We are off and running! Underground utilities (offsite) are in process and moving ahead – sewer completed. We will continue with onsite utilities and site preparation in parallel with moving buyout forward and all of the jurisdictional requirements – permitting, right of way work, etc.

Status Code Legend

On Track: Project is on schedule

At Risk: Milestones missed but date intact

Off Track: Date will be missed if action is not taken

    Activity – Month Ending 2/28

    Geotech was onsite to confirm compaction and provided a report to the City of Seattle per our special inspection requirements. All approved and cleared the way for site work.

    Underground utilities – Sewer – Tapped into the main in the street. SPU was out today 2/25- and two-line tap completed.

    Electrical engineering with Seattle City Light still moving ahead

    Application for new gas service to the project was submitted

    Mechanical engineering (wet and dry) went through the first round of revisions and is charging ahead

    Surveyor to be out to stake the property and provide an elevation marker to grade from

    Upcoming Activity Preview (March 2022)

    Underground (onsite) will continue and ground to be prepared for concrete forming

    Buyout will go into full swing in March & April and coincide with Draw # 1 (Windows will kick this off)

    Draw # 1to be submitted in March – documents provided to ownership under separate cover

    Electrical engineering with Seattle City Light still moving ahead and will require more time

    Contracts:

    Dirtwork Contract executed

    Plumbing and Mechanical Engineering contract executed

    Electrical Engineering contract executed

    Architect contract executed as consultant for life of the project

    Change Order Log (Full Summary on File):

    CO # 1 coming to the developer in the coming weeks

    Open Questions:

    None