Ashworth 5-Unit Rowhouse
Project Status Report
June 3, 2022
Overall Status: On Track
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Kevin Proefrock, Rachel Brendle, Alix Doyle
Principals: Eugene Sak, Frank Martin
Project Update:
The site has been hopping this month with crews working toward preparing the project to hit the market. The site is coming along, yet we are seeing delays due to getting the slabs repoured in units 1 & 2. We are looking to have this work wrapped in June which will allow us to deliver units as we will pour all of the onsite concrete for landscaping. See the updates below – too many to list here!
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – 5/1 – 5/31 |
● Exterior painting is 95% complete ● Electrical – main service connected ● Gutters ands scupper boxes have been installed and connected to our storm drains ● Mechanical – Units 3, 4 & 5 all have permanent heat in place ● Site drainage and grading complete in preparation for landscaping ● Units 3,4, 5 – Wrapped in preparation for flooring, carpet and countertops ● Units 3,4, 5 – Tile in guest and master bathrooms is 95% complete – will wrap when countertops are installed ● Rooftop & Porches – Decking has been delivered to the roof along with stair stringers and sub decking material (pedestal system) ● Units 1 & 2 – Upper floors have been drywalled, textured, primed and finish coated ● Units 1 & 2 – Upper floors have been prepped for tile, installation commenced ● Marketing – Updated comp set pricing sent through to ownership for review |
Upcoming Activity Preview (2-4 Weeks)
|
● Marketing – awaiting the word to bring in the staging company and get rolling ● Slab rework to wrap up this month in units 1 & 2 ● Concrete to be poured in Units 1 & 2 as well as onsite for landscaping planters, etc. ● Tile will continue in the upper floors of 1 & 2 ● Units 3, 4 & 5 – countertops and flooring to be installed first/second week of June ● Marketing plan will continue to be executed. Listing units for sale scheduled for beginning of June ● Guardrails, handrails and steel canopies will be installed this month ● Landscaping to commence at the end of June |
Contracts & Finishes: |
● Plumbing fixtures have arrived and are sitting in storage (toilets and sinks are outstanding) ● Electrical fixtures have arrived and are sitting in storage ● Carpet, Hardwood & countertops – scheduled for June install ● Appliances (Refrigerators, Dishwashers, Ranges, Microwaves and Hoods) – all in storage |
Change Order & Overages Log (Full Summary on File): |
● Overage budget has been submitted and approved. |
Open Questions: |
● None
|