Arbor Heights 9-Unit Townhome
Project Status Report
November 12, 2021
Overall Status: Green
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Still in the preliminary stages of propping up this development. We had our preconstruction meeting this week with the City of Seattle which kicked off the process and set the permits in motion, eliminating the possibility of them expiring. Site cleanup and preparation for utilities continues.
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Week Ending 11/12 |
● City of Seattle Pre-construction conference completed with Geotech, Electrician, Dirt Work Contractor and the City of Seattle. ● Site walk with Geotech to confirm strategy for site preparation in conjunction with Dirt Work Contractor & special inspections required by the City of Seattle. ● Dirt Work Contractor saw cut remaining/existing foundation wall to prepare for site work next week ● Bank construction loan continues along – all required documentation has been submitted to CFSB for review (Budget, Operating Agreement, etc.) ● All required signed documentation (Mechanic Lien, Indemnity Agreements) have been signed and are on file with title |
Upcoming Activity Preview
|
● Site preparation for utilities ● Seattle City Light application and design approval to continue ● Construction loan activity continues to track toward closing ● Project team alignment |
Contracts: |
● Dirtwork Contract in Place
|
Change Order Log (Full Summary on File): |
● None |