Ashworth 5-Unit Rowhouse
Project Status Report
January 31, 2022
Overall Status: At Risk
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Work continues throughout the project as we track toward receiving cover from the city of Seattle. We have started receiving rough in inspections in plumbing, mechanical and electrical, but we are not quite there yet. I’ve gone ahead and adjusted the schedule based on some critical items that have caused us delay.
I’m moving the project status to At Risk, which means that we will be delivering units in May versus April. I’m hoping to make up time as we work through the remaining dependencies by stacking crews in various units to knock out their individual scope. February will be a big month for us and I fully expect us to get back on track in the coming weeks.
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – 1/1 – 1/31 |
● Hardie siding has wrapped up. We are in holding pattern for the brick and wood until we pour slabs across all five units. ● Mechanical Rough-In at 85% ● Electrical Rough-In is 65% ● Water meters were ordered and paid for. SPU is talking about a mid-April/Early may installation ● Marketing continues and we are receiving inquiries – about 2-3/week ● Roof and deck metal coping installed and wrapped up ● Sewer line connection has been made and the neighbor’s line was moved onto their property ● Insulation in various areas has commenced. Full insulation will follow rough-in completion and clear to cover ● Lighting fixtures and appliances have started arriving – sitting in the warehouse waiting for installation |
Upcoming Activity Preview (2-4 Weeks)
|
● Pickup framing will continue as we track toward cover (soffiting, stairwells, etc.) ● Masonry (brick) – pushed out until middle of the month. Dependent on slabs being repoured in units 3,4 & 5. ● Insulation in various areas has commenced. Full insulation will follow rough-in completion and clear to cover ● MEP rough-in to continue/wrap up by the middle of the month (2/15) ● Inspections – will continue as necessary which will include Built Green blower tests, etc. prior to insulation. ● Marketing continues and we are receiving inquiries – about 2-3/week |
Upcoming Activity Preview (Q 1 2022 Activity)
|
● Plumbing Rough-In (Complete) ● Electrical Rough-in (In Process) – 2/15 Projected Completion ● Mechanical Rough-in (In Process) – Complete ● As needed: Inspections – Envelope, Air Seal, Wall Cover ● Siding – Brick (In Process) – 2/14 commencement, Cedar TBD ● 2/22 Insulation Start (In Process – Exterior Cantilevers) ● 3/1 – Drywall Start ● 3/15 – Interior Paint Start ● 4/1 – Flooring Start |
Contracts & Finishes: |
● Siding contract is in place ● Masonry contract is in place ● Plumbing fixtures have been ordered for all five units and are sitting in storage ● Electrical fixtures have arrived and are sitting in storage ● Interior doors – will be ordered in February 2022. ● Cabinetry & vanities ordered and due to be complete in March 2022 ● Carpet, Hardwood & countertops – ordered and scheduled for installation ● Appliances have been ordered and are arriving (sitting in storage) |
Change Order & Overages Log (Full Summary on File): |
● no additional changes at this time |
Open Questions: |
● None
|