Arbor Heights 9-Unit Townhome
Project Status Report
June 3, 2022
Overall Status: Green
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Site work wrapped up in preparation for structural concrete work this month. We’ve moved forward on concrete work and tracking nicely to get started with framing this month.
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Month Ending 5/31/22 |
● Draw # 3 funded ● Structural HW embeds landed onsite for installation ● Electrical Ufer grounds installed and inspected ● Plumbing sewer line knockouts installed at stem walls ● City of Seattle Inspections passed prior to pouring footings and stem walls ● Concrete footings and stem walls poured |
Upcoming Activity Preview (June 2022) |
● Stem wall waterproofing to commence ● Plumbing and Electrical mobilization to install sub slab work ● Slab preparation (dirtwork) and wall backfill ● Slab on Grade to be poured in accordance with plans and special inspections ● City of Seattle Inspections as required ● Lumber and Lift arrival onsite ● Framing to commence this month |
Contracts: |
● Dirt Work Contract executed ● Electrical Engineering contract executed ● Architect contract executed as consultant for life of the project ● Concrete contract executed ● Plumbing contract executed ● Fire Sprinkler contract executed ● Siding Contract (Negotiating) ● Wood and Metal Siding Sourcing (In Process) ● Roofing out for multiple bids ● Exterior Doors have been sourced |
Change Order Log (Full Summary on File): |
● CO# 1 – Permit renewal fees & plumbing and mechanical design fees ● CO # 2 – Concrete material increase, Framing labor increase, Sub Slab Insulation Increase (change of design) |
Open Questions: |
● None |