Ashworth 5-Unit Rowhouse

Project Status Report

July 16, 2021

Overall Status: Green

Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin

Project Update:

Continuing the path at Ashworth, this week was more of a demobilization/mobilization of subs transitioning as well as preparing for the upcoming body of work.

Status Code Legend

On Track: Project is on schedule

At Risk: Milestones missed but date intact

Off Track: Date will be missed if action is not taken

    Activity – Week Ending 7/16

    Concrete sub demobilization completed on Tuesday. Site is clean and looks great.

    EcoBlock wall monitoring continues with Terrane (surveyor). Next week should be the last.

    Waterproofing sub for retaining wall identified and contracted. This will be a net change to the budget of about $8,800.

    Dirtwork sub mobilized with smaller machine on Friday.

    Geotech will need to be present when retaining wall is backfilled & ecoblock wall deconstructed

    Finish look and feel delivered to ownership for review. Additional feedback provided for “smart” home additions (water sensors, smart hub technology)

    Plumbing sub aligned for a 7/26 mob date for stubbing in plumbing lines in conjunction with engineering docs.

    Upcoming Activity Preview

    Week Ending 7/23

    Crew onsite Monday to install protective caps over new concrete walls that will be exposed to prevent damage

    Footing perimeter drain, utilities, and backfill to commence. Originally set to commence prior to 7/16, but sub was late. They are mob’d now and will be start on Monday.

    Waterproofing for retaining wall

    Working through plumbing, electrical and mechanical bids, along with fixture selection, pricing and timelines

    Cabinetry refinement and pricing to commence

    Interior/Exterior door sourcing and bid pricing

    Contracts:

    Framing contract executed and in place

    Roofing contract executed

    Siding contract is on glide path for completion. Pricing is much more realistic.

    Masonry contract executed

    Windows Ordered – 2-part delivery – September & October

    Waterproofing contract executed

    Change Order Log (Full Summary on File):

    No new changes this week

    Open Questions:

    None