Ashworth 5-Unit Rowhouse

Project Status Report

September 24, 2021

Overall Status: Green

Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin

Project Update:

Framing is close to wrapping up (10/5) and we have commenced stacking subs behind the completion of framing. Updated rough scheduled through the end of the 2021 below.

Status Code Legend

On Track: Project is on schedule

At Risk: Milestones missed but date intact

Off Track: Date will be missed if action is not taken

    Activity – Weeks Ending 8/20 & 8/27

    Third Floor framing inspection passed & framing continues on the third floor and the roof TJI system.

    Built Green kickoff took place with Evergreen Certified, LLC – our required consultant. Chain team is pivoting to make the necessary changes to achieve our Built Green Certifications

    HVAC contract executed and site meeting to start planning out mechanical routing

    Continued the mobilization discussions with Siding, Masonry and Roofing sub-contractors for October dates

    Upcoming Activity Preview (2 Weeks)

    Framing due to wrap up – two remaining lumber drops

    First wave of windows due to arrive on site – 10/28

    Waterproofing to commence

    Siding sub-contractor to land onsite and start with building wrap

    Inspections – Final Sheer Wall, Framing Final, Roof Cover, Siding Cover

    Sewer line & Utility Continuation

    Upcoming Activity Preview (Q 4 Activity)

    10/11Roofing Start

    10/15 – Plumbing Rough-In Start, Second Window Delivery Scheduled

    10/18 – Mechanical Start

    10/18 – Electrical Rough-in Start

    10/25 – Masonry Start

    11/1 – Insulation Start

    11/11 – Inspections – Envelope, Air Seal, Wall Cover

    11/30 – Drywall Start

    Contracts:

    Roofing contract is in place

    Siding contract is in place

    Masonry contract is in place

    Windows Ordered – 2-part delivery – September & October

    Plumbing contract executed & work has commenced

    Exterior doors have been ordered (8/27) – 5 week lead time

    HVAC contract is in place

    Insulation contract is in place

    Drywall contract is in place

    Change Order Log (Full Summary on File):

    HVAC bid came in at $90,000 – this is approximately $20,000 higher than our original estimate.

    Open Questions:

    Interior finishes – still underway on wrapping this up, but all in flight.