Ashworth 5-Unit Rowhouse
Project Status Report
September 24, 2021
Overall Status: Green
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Framing is close to wrapping up (10/5) and we have commenced stacking subs behind the completion of framing. Updated rough scheduled through the end of the 2021 below.
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Weeks Ending 8/20 & 8/27 |
● Third Floor framing inspection passed & framing continues on the third floor and the roof TJI system. ● Built Green kickoff took place with Evergreen Certified, LLC – our required consultant. Chain team is pivoting to make the necessary changes to achieve our Built Green Certifications ● HVAC contract executed and site meeting to start planning out mechanical routing ● Continued the mobilization discussions with Siding, Masonry and Roofing sub-contractors for October dates |
Upcoming Activity Preview (2 Weeks) |
● Framing due to wrap up – two remaining lumber drops ● First wave of windows due to arrive on site – 10/28 ● Waterproofing to commence ● Siding sub-contractor to land onsite and start with building wrap ● Inspections – Final Sheer Wall, Framing Final, Roof Cover, Siding Cover ● Sewer line & Utility Continuation |
Upcoming Activity Preview (Q 4 Activity) |
● 10/11 – Roofing Start ● 10/15 – Plumbing Rough-In Start, Second Window Delivery Scheduled ● 10/18 – Mechanical Start ● 10/18 – Electrical Rough-in Start ● 10/25 – Masonry Start ● 11/1 – Insulation Start ● 11/11 – Inspections – Envelope, Air Seal, Wall Cover ● 11/30 – Drywall Start |
Contracts: |
● Roofing contract is in place ● Siding contract is in place ● Masonry contract is in place ● Windows Ordered – 2-part delivery – September & October ● Plumbing contract executed & work has commenced ● Exterior doors have been ordered (8/27) – 5 week lead time ● HVAC contract is in place ● Insulation contract is in place ● Drywall contract is in place |
Change Order Log (Full Summary on File): |
● HVAC bid came in at $90,000 – this is approximately $20,000 higher than our original estimate. |
Open Questions: |
● Interior finishes – still underway on wrapping this up, but all in flight. |