Arbor Heights 9-Unit Townhome
Project Status Report
April 29, 2022
Overall Status: Green
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Sitework continues in preparation for concrete. April was a big month in that we have our civil work wrapped along with the site detention facility in place. We have a bit of a delay due to sub backlog, but concrete will start in May.
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Month Ending 3/31 |
● Draw # 2 funded ● Detention facility installed and in place along with pumping station ● Building pads continued to be prepped for concrete ● Electrical get start permitting received for sub slab/underground conduits ● Plumbing get start permitting received for sub/slab/underground piping |
Upcoming Activity Preview (May 2022)
|
● Concrete forming to commence with pouring to follow toward the middle of the month ● Plumbing and Electrical mobilization to install sub slab work ● Lumber packages will look to land onsite toward the end of the month with a potential for framing to get rolling in May. |
Contracts: |
● Dirt Work Contract executed ● Electrical Engineering contract executed ● Architect contract executed as consultant for life of the project ● Concrete contract executed ● Plumbing contract executed ● Fire Sprinkler contract executed
|
Change Order Log (Full Summary on File): |
● N/A |
Open Questions: |
● None |