Ashworth 5-Unit Rowhouse
Project Status Report
April 29, 2022
Overall Status: On Track
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Big month onsite wrapping up the entire exterior along with moving units 3,4,5 closer to completion. Cabinetry is in place, doors and millwork complete, tile is wrapped, along with painting in each of these units. Work will continue to wrap these up so we can start listing them for sale toward the end of May. Units 1 & 2 are also in flight and will follow shortly behind. Looking great out there!
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – 4/1 – 4/29 |
● Brick Masonry work wrapped up and looks great! ● Wood (Cedar) Siding also wrapped up this month ● Units 3,4, 5 – Drywall has wrapped and walls have been textured and primed ● Units 3,4, 5 – Interior doors and Millwork has been installed ● Units 3,4, 5 – Kitchen cabinetry and bathroom vanities have been installed ● Units 3,4, 5 – Finish Painting (2 of 3 coats) has completed along with all millwork caulked, sanded and painted ● Units 3,4, 5 – Tile in guest and master bathrooms is 70% complete ● Units 1 & 2 Upper floors have drywall and first coat of mud on floors 2 and 3 ● Marketing – Real estate signage has been installed on the site facing 80th ● Marketing – Updated comp set pricing sent through to ownership for review ● Electrical – main service was inspected and approved. Awaiting Seattle City Light to connect to our new meter pack. |
Upcoming Activity Preview (2-4 Weeks)
|
● Slab rework for the first floor of units 1 & 2 to commence. Will look to wrap by end of May & pour the new slabs. These units will continue through the end of June to wrap. ● Tile to continue in all units. Looking to wrap up in May. ● Units 3, 4 & 5 will largely wrap by the end of May complete with HW flooring, countertops and MEP trim out ● Marketing plan will continue to be executed. Listing units for sale scheduled for beginning of June ● Additional site work and final grading to wrap beginning of May paving the way for concrete and landscaping |
Contracts & Finishes: |
● Plumbing fixtures have arrived and are sitting in storage (toilets and sinks are outstanding) ● Electrical fixtures have arrived and are sitting in storage ● Cabinetry & vanities – delivered, need to be installed ● Carpet, Hardwood & countertops – scheduled for May install ● Appliances (Refrigerators, Dishwashers, Ranges, Microwaves and Hoods) – all in storage |
Change Order & Overages Log (Full Summary on File): |
● Chain is currently working out the final estimate and overages to wrap the project. |
Open Questions: |
● None
|