Arbor Heights 9-Unit Townhome
Project Status Report
September 2, 2022
Overall Status: Green
Project Name: Arbor Heights Townhome
Project Team: Frank Martin, Erin Cassidy, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update: Vertical construction has begun! We were able to get our slabs poured and our sewers in paving the way for framing. Make sure to tune into the cameras for live action! 😊
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Month Ending 9/2/22 |
● Sub slab ground preparation complete and signed off by Geotech ● Sub slab insulation, rebar and vapor barrier installed ● Sewer installation completed and inspected – passed – backfill complete ● Concrete slabs prepped, inspected and complete – concrete poured ● Telehandler onsite along with recycling container for debris ● First three lumber drops took place ● Framing has commenced – walls are up for buildings 1 & 2 for the first floor ● Exterior doors are ready and to be delivered onsite 9/29 ● Windows are ready and to be delivered onsite the week of 9/23 |
Upcoming Activity Preview (September 2022)
|
● Framing will continue through the month of September and into October ● Project buyout to continue with interior finishes ● Slab insulation and rebar installation (special inspections required) |
Contracts: |
● Dirt Work Contract executed ● Electrical Engineering contract executed ● Architect contract executed as consultant for life of the project ● Concrete contract executed ● Plumbing contract executed ● Fire Sprinkler contract executed ● Siding Contract executed ● Wood and Metal Siding Sourcing – complete ● Roofing executed ● Exterior Doors ready, but have delayed shipment to end of September ● Window package ready, but have delayed shipment to end of September ● Cabinetry bids are in and under review ● Countertops – bids requested ● Drywall – additional bids requested |
Change Order Log (Full Summary on File): |
● CO# 1 – Permit renewal fees & plumbing and mechanical design fees ● CO # 2 – Concrete material increase, Framing labor increase, Sub Slab Insulation Increase (change of design) ● CO # 3 – Concrete waterproofing ● CO # 4 – Pending review – concrete, lumber and structural hardware price increases |
Open Questions: |
● None |