Arbor Heights 9-Unit Townhome

Project Status Report

October 6, 2022

Overall Status: Green

Project Name: Arbor Heights Townhome
Project Team: Frank Martin, Erin Cassidy, Kevin Proefrock
Principals: Eugene Sak, Frank Martin

Project Update: Making great progress onsite with framing. We are now wrapping up walls on the second floor and getting ready to receive the floor systems for the third floor. Looking great out there and tracking toward getting dried in prior to the middle of November.

 

Status Code Legend

On Track: Project is on schedule

At Risk: Milestones missed but date intact

Off Track: Date will be missed if action is not taken

    Activity – Month Ending 10/6/22

    Lumber continues to drop as needed per schedule

    Framing continues – second level walls are up

    Exterior doors received and staged in each of the units

    Windows are ready and to be delivered onsite the week of 11/9

    Upcoming Activity Preview (October 2022)

    Framing will continue and should wrap toward the end of October.

    Roofing contractor to mobilize later this month

    Project buyout will continue through the end of the year

    Contracts:

    Dirt Work Contract executed

    Electrical Engineering contract executed

    Architect contract executed as consultant for life of the project

    Concrete contract executed

    Plumbing contract executed

    Mechanical contract executed

    Fire Sprinkler contract executed

    Siding Contract executed

    Wood and Metal Siding Sourcing – complete

    Roofing contract executed

    Exterior Doors delivered to the site

    Window package ready, set to deliver on 11/9

    Cabinetry bid accepted and working on contracting

    Countertops – bids received, reviewing now.

    Drywall – additional bids requested

    Change Order Log (Full Summary on File):

    CO# 1 – Permit renewal fees & plumbing and mechanical design fees

    CO # 2 – Concrete material increase, Framing labor increase, Sub Slab Insulation Increase (change of design)

    CO # 3 – Concrete waterproofing

    CO # 4 – Pending review – concrete, lumber and structural hardware price increases

    Open Questions:

    None