Arbor Heights 9-Unit Townhome
Project Status Report
October 6, 2022
Overall Status: Green
Project Name: Arbor Heights Townhome
Project Team: Frank Martin, Erin Cassidy, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update: Making great progress onsite with framing. We are now wrapping up walls on the second floor and getting ready to receive the floor systems for the third floor. Looking great out there and tracking toward getting dried in prior to the middle of November.
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Month Ending 10/6/22 |
● Lumber continues to drop as needed per schedule ● Framing continues – second level walls are up ● Exterior doors received and staged in each of the units ● Windows are ready and to be delivered onsite the week of 11/9 |
Upcoming Activity Preview (October 2022)
|
● Framing will continue and should wrap toward the end of October. ● Roofing contractor to mobilize later this month ● Project buyout will continue through the end of the year |
Contracts: |
● Dirt Work Contract executed ● Electrical Engineering contract executed ● Architect contract executed as consultant for life of the project ● Concrete contract executed ● Plumbing contract executed ● Mechanical contract executed ● Fire Sprinkler contract executed ● Siding Contract executed ● Wood and Metal Siding Sourcing – complete ● Roofing contract executed ● Exterior Doors delivered to the site ● Window package ready, set to deliver on 11/9 ● Cabinetry bid accepted and working on contracting ● Countertops – bids received, reviewing now. ● Drywall – additional bids requested |
Change Order Log (Full Summary on File): |
● CO# 1 – Permit renewal fees & plumbing and mechanical design fees ● CO # 2 – Concrete material increase, Framing labor increase, Sub Slab Insulation Increase (change of design) ● CO # 3 – Concrete waterproofing ● CO # 4 – Pending review – concrete, lumber and structural hardware price increases |
Open Questions: |
● None |