Arbor Heights 9-Unit Townhome

Project Status Report

November 1, 2022

Overall Status: Green

Project Name: Arbor Heights Townhome
Project Team: Frank Martin, Erin Cassidy, Kevin Proefrock
Principals: Eugene Sak, Frank Martin

Project Update: Framing continued for the month of October with a wrap date to be the second week of November. We have begun to line up the envelope subs to start work shortly after framing completes. We are off to the races this month to get the building dried in!

 

Status Code Legend

On Track: Project is on schedule

At Risk: Milestones missed but date intact

Off Track: Date will be missed if action is not taken

    Activity – Month Ending 10/31/22

    Lumber continues to drop as needed per schedule, however we will have some lumber returned for a savings. Final reconciliation will be outlined.

    Framing continues – second, third levels complete. Roof framing in process.

    Cedar and Metal siding orders released

    Buyout continues closing out on cabinetry and HVAC.

    Upcoming Activity Preview (November 2022)

    Framing ongoing – looking to wrap up by the week of November 7th

    Roofing, Siding and Window Installer Subs to mobilize and begin scope

    Windows are to be delivered onsite the week of 11/9

    Project buyout will continue through the end of the year

    Contracts:

    Dirt Work Contract executed

    Electrical Engineering contract executed

    Architect contract executed as consultant for life of the project

    Concrete contract executed

    Plumbing contract executed

    Mechanical contract executed

    Fire Sprinkler contract executed

    Siding Contract executed

    Wood and Metal Siding Sourcing – complete

    Roofing contract executed

    Exterior Doors delivered to the site

    Window package ready, set to deliver on 11/9

    Cabinetry contract executed

    Countertops – bids received, reviewing now.

    Drywall – additional bids requested

    Change Order Log (Full Summary on File):

    CO# 1 – Permit renewal fees & plumbing and mechanical design fees

    CO # 2 – Concrete material increase, Framing labor increase, Sub Slab Insulation Increase (change of design)

    CO # 3 – Concrete waterproofing

    CO # 4 – Pending review – concrete, lumber and structural hardware price increases

    Open Questions:

    None