Arbor Heights 9-Unit Townhome

Project Status Report

January 13, 2023

Overall Status: Green

Project Name: Arbor Heights Townhome
Project Team: Frank Martin, Erin Cassidy, Kevin Proefrock
Principals: Eugene Sak, Frank Martin

Project Update: Happy New Year! Nice to have the holidays and a crazy spell of weather behind us. It’s still wet, but we seem to be clear of ice storms and snow. ?
Job progress continues with the windows at about 90%, the roofing at 66% and the building wrap/siding commencing. Plumbing rough-in will wrap the week of 1/23 and HVAC rough-in will follow. Electrical rough-in is underway as well. Our goal is to be signed off to cover walls on 3/1/23.

Status Code Legend

On Track: Project is on schedule

At Risk: Milestones missed but date intact

Off Track: Date will be missed if action is not taken

    Activity – Month Ending 1/15/23

    Various pick-up framing continues throughout the project in preparation for the various trades

    Roofing – West and Central buildings are complete. East Building and all remaining decks, eyebrows will wrap the week of 2/2.

    Cedar and Metal siding arrived and are onsite

    Plumbing rough-in continues and is due to wrap the week of 1/23

    Electrical rough-in started on 1/9 and is well underway

    HVAC is due to commence toward the end of this month following plumbing wrap up

    Buyout continues based on interior elevations, finish selections, etc.

    Upcoming Activity Preview (January/February 2023)

    Framing will most likely be ongoing for various pickup activities

    Siding will continue onsite through early March

    Windows and Doors will continue and wrap in February

    Fire Sprinkler rough-in to kick off in early February for commercial unit

    Cover and MEP inspections – looking to have them at the end of February

    Insulation will kick off in February

    Project buyout will most likely continue as needed

    Street work to connect storm drain to commence in February

    Contracts:

    Dirt Work Contract executed

    Electrical Engineering contract executed

    Architect contract executed as consultant for life of the project

    Concrete contract executed

    Plumbing contract executed

    Mechanical contract executed

    Fire Sprinkler contract executed

    Siding Contract executed

    Wood and Metal Siding Sourcing – complete

    Roofing contract executed

    Exterior Doors delivered to the site

    Cabinetry contract executed

    Countertops – bids received, reviewing now.

    Drywall – Sub selected, pricing is in negotiation

    Change Order Log (Full Summary on File):

    CO# 1 – Permit renewal fees & plumbing and mechanical design fees

    CO # 2 – Concrete material increase, Framing labor increase, Sub Slab Insulation Increase (change of design)

    CO # 3 – Concrete waterproofing

    CO # 4 – Pending review – concrete, lumber and structural hardware price increases

    Open Questions:

    None