Ashworth 5-Unit Rowhouse
Project Status Report
July 23, 2021
Overall Status: Green
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Made some great headway this week in preparation for pouring the slab and coordinating framing start. See progress bullets below.
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Week Ending 7/23 |
● Concrete waterproofing took place on the retaining wall as well as the east and west sides of the building. See photos – Sikaflex product with drain mat. ● EcoBlock wall monitoring took place – Geotech cleared us to stand down next week in anticipation of utilities and backfill. Geotech onsite to review retaining wall waterproofing and backfill. ● Dirt work sub completed backfill with native soil. CAD truck scheduled on Monday to bring in structural fill. See photos attached. ● Plumbing bid secured and contract signed. ● Lumber bids are being shopped through 2 other yards locally. Takeoff sent to Eugene for review. ● Conversation continues around lumber prices dropping, however the yards are not seeing the same drop on engineered lumber – TJI’s, Parallams, and Gluelams. ● Pre-ordered Gluelam beams for project as they are a long lead time item for Floor 1. Holding on releasing lumber order until we vet pricing ● Electrical switching and lighting plans delivered to the engineer for finalization of plans. |
Upcoming Activity Preview Week Ending 7/30 |
● Plumbing & Electrical sub aligned for a 7/28 mob date for stubbing in plumbing lines in conjunction with engineering docs. ● Footing perimeter drain, utilities, and backfill to commence. ● Cabinetry refinement and pricing to commence ● HVAC bid refinement – should have this back this week. ● Interior/Exterior door sourcing and bid pricing ● Slabs scheduled to be poured on 8/6 ● Framing scheduled to commence on 8/9 |
Contracts: |
● Framing contract executed ● Roofing contract executed ● Siding contract is in place ● Masonry contract executed ● Windows Ordered – 2-part delivery – September & October ● Plumbing contract executed |
Change Order Log (Full Summary on File): |
● Slab insulation – 2” rigid foam + vapor barrier – $6,245
|
Open Questions: |
● None |