Ashworth 5-Unit Rowhouse
Project Status Report
July 9, 2021
Overall Status: Green
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Another week of big milestones completed/underway. Concrete sub will demobilize next week to allow for utilities and backfill. Next time they are back, we will be pouring the slabs on grade. Most likely in 2-3 weeks.
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Week Ending 7/9 |
● City Inspection of stem/retaining walls with City of Seattle Passed ● Stem walls poured on 7/9. Plan will be to strip, pack and be clear of the site on 7/13 ● EcoBlock wall monitoring continues with Terrane (surveyor). Next week should be the last week as we are going to begin backfilling ● Window package ordered and paid for |
Upcoming Activity Preview Week Ending 7/16 |
● Footing perimeter drain, utilities, and backfill to commence ● Retaining wall inspection with City of Seattle scheduled on 7/7 ● Continuing with design & mood boards – review on 7/15 |
Contracts: |
● Framing contract executed and in place ● Roofing contract executed ● Siding contract is currently being negotiated. Had meeting today with new Siding outfit to find alternative to bring cost down. ● Masonry contract executed ● Windows Ordered – 2-part delivery – September & October |
Change Order Log (Full Summary on File): |
● Retaining wall waterproofing. Not detailed on the plans, but will be required. Working through financial & timing impact now.
|
Open Questions: |
● Draw # 3 Release – where are we with this? |