Ashworth 5-Unit Rowhouse
Project Status Report
October 15, 2021
Overall Status: Green
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Still have a bit of framing left to do – proposed framing completion is Wednesday 10/20. Delayed due to lumber delivery to the top level which required two separate crane assists. Exterior trades are lining up as we speak along with interior MEP rough in trades. Going to be a flurry of activity the next
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Weeks Ending 8/20 & 8/27 |
● Framing is still ongoing, however the crew has all of the roofs in place for each unit and is wrapping up the parapet walls now. Still a bit of pick up framing to complete inside around the stairwells along with backing, blocking and quality control checks ● Windows have arrived onsite and the crew has begun waterproofing in preparation for setting them. ● Second wave of windows due to arrived on 10/12 – All windows onsite now. ● Electrical team has begun to nail in boxes according to engineered layout ● Fence was removed & parcel boundary mapped in preparation for sewer line replacement (neighbor) and setting ● Site visit with Architect to review project and HVAC penetrations to ensure minimal impact to units ● Insulation of parapet walls wrapped up today to allow for closing them up prior to roofing ● Plumbing team site meeting this week confirmed start date and adjustments to plans |
Upcoming Activity Preview (2 Weeks) |
● Framing due to wrap up completely ● Building wrap and rainscreen installation ● Waterproofing and window setting to wrap up in the coming weeks ● Roofing mobilization 10/25 ● Inspections – Final Sheer Wall, Framing Final, Roof Cover, Siding Cover ● Neighboring sewer line to be installed next week and tie into Ashworth & the SPU main |
Upcoming Activity Preview (Q 4 Activity) |
● 10/25 – Roofing Start ● 11/1 – Plumbing Rough-In Start ● 11/8 – Mechanical Start ● 10/12 – Electrical Rough-in Start ● 10/25 – Masonry Start ● 10/15 – Insulation Start ● 11/11 – Inspections – Envelope, Air Seal, Wall Cover ● 12/6 – Drywall Start |
Contracts: |
● Roofing contract is in place ● Siding contract is in place ● Masonry contract is in place ● Windows Ordered – 2-part delivery – September & October ● Plumbing contract executed & work has commenced ● Exterior doors scheduled for d ● HVAC contract is in place ● Insulation contract is in place ● Drywall contract is in place |
Change Order & Overages Log (Full Summary on File): |
● Buyout log is currently tracking a $73,000 overage due to supply chain constraints and increased sub-contractor costs ● Change order log is tracking $55,000 in overages |
Open Questions: |
● None at the moment |