Arbor Heights 9-Unit Townhome
Project Status Report
March 31, 2022
Overall Status: Green
Project Name: Ashworth Townhome Project
Project Team: Frank Martin, Erin Cassidy, Jon Rasnic, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update:
Civil work continued this month wrapping up with the detention facility. In the coming weeks we will prepare for concrete sub mobilization and structural forming and pouring. Buyout continues with sub evaluation, bid review and contract execution.
Status Code Legend
● On Track: Project is on schedule
● At Risk: Milestones missed but date intact
● Off Track: Date will be missed if action is not taken
Activity – Month Ending 3/31 |
● Site detention facility was delivered & installed this week as well as signed off by City of Seattle ● Gas service line(s) location have been outlined with Puget Sound Energy ● Windows and Door have been ordered and paid for – delivery estimated in June/July ● Mechanical engineering (wet and dry) wrapped up in March. Plans distributed to subs. ● Draw # 1 funded, Draw # 2 submitted |
Upcoming Activity Preview (April/May 2022)
|
● Ground to be prepared for concrete forming – this will wrap in April ● Water service application will be submitted this month pending Water Availability Certificate ● Concrete sub to mobilize and prepare for pouring ● Electrical engineering still underway. Good news – project will not require an underground vault (potential savings) |
Contracts: |
● Dirt Work Contract executed ● Electrical Engineering contract executed ● Architect contract executed as consultant for life of the project ● Concrete contract executed ● Plumbing contract executed
|
Change Order Log (Full Summary on File): |
● N/A |
Open Questions: |
● None |