Arbor Heights 9-Unit Townhome
Project Status Report
January 13, 2023
Overall Status:Β Green
Project Name: Arbor Heights Townhome
Project Team: Frank Martin, Erin Cassidy, Kevin Proefrock
Principals: Eugene Sak, Frank Martin
Project Update: Happy New Year! Nice to have the holidays and a crazy spell of weather behind us. Itβs still wet, but we seem to be clear of ice storms and snow. π
Job progress continues with the windows at about 90%, the roofing at 66% and the building wrap/siding commencing. Plumbing rough-in will wrap the week of 1/23 and HVAC rough-in will follow. Electrical rough-in is underway as well. Our goal is to be signed off to cover walls on 3/1/23.
Status Code Legend
β On Track: Project is on schedule
β At Risk: Milestones missed but date intact
β Off Track: Date will be missed if action is not taken
Activity β Month Ending 1/15/23 |
β Various pick-up framing continues throughout the project in preparation for the various trades β Roofing β West and Central buildings are complete. East Building and all remaining decks, eyebrows will wrap the week of 2/2. β Cedar and Metal siding arrived and are onsite β Plumbing rough-in continues and is due to wrap the week of 1/23 β Electrical rough-in started on 1/9 and is well underway β HVAC is due to commence toward the end of this month following plumbing wrap up β Buyout continues based on interior elevations, finish selections, etc. |
Upcoming Activity Preview (January/February 2023)
|
β Framing will most likely be ongoing for various pickup activities β Siding will continue onsite through early March β Windows and Doors will continue and wrap in February β Fire Sprinkler rough-in to kick off in early February for commercial unit β Cover and MEP inspections β looking to have them at the end of February β Insulation will kick off in February β Project buyout will most likely continue as needed β Street work to connect storm drain to commence in February |
Contracts: |
β Dirt Work Contract executed β Electrical Engineering contract executed β Architect contract executed as consultant for life of the project β Concrete contract executed β Plumbing contract executed β Mechanical contract executed β Fire Sprinkler contract executed β Siding Contract executed β Wood and Metal Siding Sourcing β complete β Roofing contract executed β Exterior Doors delivered to the site β Cabinetry contract executed β Countertops β bids received, reviewing now. β Drywall β Sub selected, pricing is in negotiation |
Change Order Log (Full Summary on File): |
β CO# 1 β Permit renewal fees & plumbing and mechanical design fees β CO # 2 β Concrete material increase, Framing labor increase, Sub Slab Insulation Increase (change of design) β CO # 3 β Concrete waterproofing β CO # 4 β Pending review β concrete, lumber and structural hardware price increases |
Open Questions: |
β None |